Description
Combined Synopsis/Solicitation for commercial goods and services IAW FAR part 12. Defense Supply Center Richmond (DSCR) B66C HVAC Packaging Unit Replacement This is a solicitation for construction prepared in accordance with the format in FAR Part 36, as supplemented with additional information included in this notice. The solicitation number SP4703-26-Q-0043 is issued as a request for quote (RFQ). The resulting contract will be a firm-fixed price award with a period of performance of 90 days after the Notice to Proceed. 1. OBJECTIVES Demolish and replace a 20-Ton indoor package unit with a brand new, fully functional, 20-Ton indoor package unit with a heat pump. The new unit must be integrated into the current unit's operating system. 2. BACKGROUND The current steam powered 20-Ton Package unit has been subjected to condensation and leaks overflowing onto the floor. The excessive amount of water has led to the surrounding area being damaged and repaired multiple times. 3. SPECIFIC REQUIREMENTS The contractor is responsible for all material, hardware, tools, labor, etc. The contractor shall supply a dumpster and a portable bathroom for the duration of the project. All demolished material shall be disposed of off-site. The areas that were disturbed shall be fixed to restore original condition. All hardware and equipment shall be fully operational after turnover. The contractor shall: 3.1 Mobilization • Submit any documentations required to execute this project, i.e. certifications, equipment submittals, project schedule, etc. • Deliver any equipment that is to be used during the execution of this project, i.e. scaffolds/lifts, safety equipment, tools, etc. 3.2 Site Preparation and Protection • Install a barrier to isolate the work area to ensure anyone not authorized enters the constructions zone. • Display signage warning people that authorization and Personal Protective Equipment are required when entering a construction zone. 3.3 HVAC Demolition • Discharge the current unit refrigerant into cylinders provided by the installation. Once discharged, the refrigerant is to be documented and turned into the installation via the Project Manager. • Remove the current 20-Ton Steam Package unit in Bay D. • Cut and cap the steam lines that were powering the current unit. • Dispose of all the debris off site. 3.4 Flooring Repair • Inspect the affected area to determine the extent of water erosion and surface deterioration. • Document existing conditions (photos, measurements, reports, etc.). • Mechanically grind damaged area to expose sounds substrate and clean the area using an appropriate method i.e. vacuuming, pressure washing, etc. o Give 48-hour notice to the Project Manager for inspection and approval. o No harmful chemicals may be used. • Fill in the removed and eroded sections using appropriate concrete repair material so that the area is level and smooth to match the adjacent surface. o Allow adequate cure time per manufacture specification. • Grin…
Classification
Place of Performance
Contracting Office
Contacts
Attachments (3)