$64K
Obligations · USAspending
Actions May '20 – Feb '22
4
Contract awards · USAspending
—
SAM.gov award notices · 12 mo
Top agencies
By obligations · USAspending, all years
- Department of Agriculture$45K · 2 awards
- General Services Administration$20K · 2 awards
Top NAICS
By obligations · USAspending, all years
Recent awards
Latest contract actions by start date · USAspending
| Award | Agency | Start | Amount |
|---|---|---|---|
| 47PJ0022P0014 | Public Buildings Service | 02/15/2022 | $13K |
| 12805B22P0041 | Agricultural Research Service | 02/01/2022 | $20K |
| 47PJ0020P0111 | Public Buildings Service | 07/24/2020 | $7K |
| 12661220P0022 | Agricultural Research Service | 05/22/2020 | $25K |
Subcontracts received
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
$61K
Received · FY2025–FY2027
$61K
Received · all years
4
Subawards
1
Prime
Top primes
| Prime contractor | Total |
|---|---|
| FIRELAKE CONSTRUCTION INC | $61K |
Most recent
- −$410"2” INSULATION, WALL THIMBLES REDUCTION IN SUBCONTRACT VALUE TO ACCOUNT FOR INTERSTATE’S ADDITIONAL COST OF PROCURING THE 2” INSULATION TO MEET SPEC. WHEN INTERSTATE HAD OFFERED TO PROCURE SOME OF THE INSULATION DUE TO THE DELAY IN GENERATOR SHIP DATES, A REDUCTION TO AGASSIZ’ CONTRACT VALUE WAS NOT MADE. THEREFORE, WE ARE REDUCING CONTRACT VALUE BY THE DELTA OF 1” VS. 2”. (-$3,600.00) INCREASE IN SUBCONTRACT VALUE TO ACCOUNT FOR RE-BUILDING OF THE WALL THIMBLES. 14 GAUGE STEEL, WELDING, WELDING CONSUMABLES, AND HIGH TEMP BLACK SPRAY PAINT. ($3,190.00) $$$: -($410.00)"
- $1K"PROVIDE AND INSTALL GAS PIPING, INSULATION , DUCTWORK LOUVERS AND DAMPERS FOR THE 2 GENERATORS 1-STEAM UNIT HEATER PROVIDE AND INSTALL STEAM AND CONDENSATE PIPING FOR STEAM UNIT HEATER PROVIDE AND INSTALL TRENCH DRAINS AND SAND OIL SEPARATOR AS INDICATED ON THE PLANS WITH ALL ASSOCIATED UNDERGROUND PLUMBING AND TIE INTO SEWER 5 OUTSIDE OF BUILDING THAT IS DONE BY OTHERS AND NOT INCLUDED IN THIS BID PRICE COORDINATION WITH XCEL GAS COMPANY TO SHORTEN UP SERVICE AND SET METER IN NEW LOCATION INSTALL MUFFLERS AND SILENCERS FOR GENERATORS (PROVIDED WITH GENERATOR) PROVIDE AND INSTALL 5 INCH PIPE AND FITTINGS FOR TYING THE GENERATOR EXHAUST INTO MUFFLERS AND SILENCERS "
- $20K"PROVIDE AND INSTALL GAS PIPING, INSULATION , DUCTWORK LOUVERS AND DAMPERS FOR THE 2 GENERATORS 1-STEAM UNIT HEATER PROVIDE AND INSTALL STEAM AND CONDENSATE PIPING FOR STEAM UNIT HEATER PROVIDE AND INSTALL TRENCH DRAINS AND SAND OIL SEPARATOR AS INDICATED ON THE PLANS WITH ALL ASSOCIATED UNDERGROUND PLUMBING AND TIE INTO SEWER 5 OUTSIDE OF BUILDING THAT IS DONE BY OTHERS AND NOT INCLUDED IN THIS BID PRICE COORDINATION WITH XCEL GAS COMPANY TO SHORTEN UP SERVICE AND SET METER IN NEW LOCATION INSTALL MUFFLERS AND SILENCERS FOR GENERATORS (PROVIDED WITH GENERATOR) PROVIDE AND INSTALL 5 INCH PIPE AND FITTINGS FOR TYING THE GENERATOR EXHAUST INTO MUFFLERS AND SILENCERS "
- $40K"PROVIDE AND INSTALL GAS PIPING, INSULATION , DUCTWORK LOUVERS AND DAMPERS FOR THE 2 GENERATORS 1-STEAM UNIT HEATER PROVIDE AND INSTALL STEAM AND CONDENSATE PIPING FOR STEAM UNIT HEATER PROVIDE AND INSTALL TRENCH DRAINS AND SAND OIL SEPARATOR AS INDICATED ON THE PLANS WITH ALL ASSOCIATED UNDERGROUND PLUMBING AND TIE INTO SEWER 5 OUTSIDE OF BUILDING THAT IS DONE BY OTHERS AND NOT INCLUDED IN THIS BID PRICE COORDINATION WITH XCEL GAS COMPANY TO SHORTEN UP SERVICE AND SET METER IN NEW LOCATION INSTALL MUFFLERS AND SILENCERS FOR GENERATORS (PROVIDED WITH GENERATOR) PROVIDE AND INSTALL 5 INCH PIPE AND FITTINGS FOR TYING THE GENERATOR EXHAUST INTO MUFFLERS AND SILENCERS "