Back to contract actions
Awarding Agency
Sub-Agency
Department of State
Start Date
December 7, 2017
End Date
December 31, 2026
NAICS
PSC
C211
Description
THIS TASK ORDER PROVIDES FUNDING FOR THE CONSTRUCTION PHASE FOR SITE COMMISSIONING SERVICES ERBIL NCC PROJECT.
Transactions (6)
| Date | Mod # | Obligation |
|---|---|---|
| Dec 7, 2017 | 0 | +$1,245,083 |
| Apr 19, 2022 | P00001 | +$927,087 |
| Jul 12, 2022 | P00002 | +$0 |
| Jul 2, 2025 | P00003 | +$948,973 |
| Mar 18, 2026 | P00004 | +$761,411 |
| Jun 24, 2026 | P00005 | +$0 |