PIID47PM0721F0094DELIVERY ORDER
$70,835,855.81
Awarding Agency
Sub-Agency
Public Buildings Service
Start Date
May 1, 2021
End Date
April 30, 2046
NAICS
PSC
B540

Description

NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION SERVICES.

Transactions (23)
DateMod #Obligation
Mar 31, 20210+$1,315,833
May 4, 2021PA0001+$0
Nov 12, 2021PS0002+$0
Dec 23, 2021PS0003+$1,395,110
Jan 19, 2022PA0004+$0
Mar 22, 2022PS0005+$0
Sep 20, 2022PO0006+$55,867
Jul 18, 2023PO0007+$134,000
Sep 29, 2023PO0008+$1,648,011
Nov 17, 2023PS0009+$22,688,397
May 15, 2024PS0010+$0
Jun 7, 2024PO0011+$7,723,285
Aug 21, 2024PA0012+$40,813
Sep 18, 2024PS0014+$61,952
Sep 28, 2024PA0015-$40,813
Jan 17, 2025PS0016+$18,855,230
Jun 6, 2025PO0017+$5,963,625
Jul 16, 2025PA0021+$0
Oct 17, 2025PS0024+$4,934,731
Dec 12, 2025PO0025+$0
Dec 23, 2025PS0026+$0
Mar 20, 2026PA0028+$0
May 4, 2026PA0029+$6,059,815
Subcontractors 7$42,369,584 total

Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete

SubcontractorAmount
UEI N6RSC55XNTA5
Rrb & neob water softener salt delivering onsite.
$40,000
UEI N6RSC55XNTA5
Mechanical, hvac and electrical labor for espc project in washington dc.
$1,876,623
UEI V23JRXHTVN33
Scheduled preventive maintenance & monitoring services
$84,979
UEI Z9GPZQ5PJQG4
Commissioning of five (5) boilers in eeob with 12 pumps.
$134,540
UEI T398ADL1NSP3
Mechanical- cooling tower replacement, chill water pump replacement, prep and paint ct steel, furnish and install basin filtration system, replace butterfly valves, replace gear operated butterfly valves, and replace corroded piping.
$12,172,369
UEI T398ADL1NSP3
Decouple whc from GSA hotd steam plant
$27,308,800
UEI NTW5TQ1UJF57
Neob 9th and 10th floor vista bas replacement. eeob north court cooling tower replacement.
$752,273