FedOps logoFedOps
Back to contract actions
PIID69056725F00017NDELIVERY ORDER

HDR ENGINEERING, INC.

UEI: USHVJJK5QXH4
$395,477.59
Awarding Agency
Sub-Agency
Federal Highway Administration
Start Date
April 17, 2025
End Date
January 18, 2026
NAICS
PSC
C219

Description

MT FLAP VALLEY 20(1), DUCK CREEK ROAD CONSULTANT PROJECT ENGINEER (CPE) AND CONSULTANT INSPECTOR (CI) SERVICES

Transactions (2)
DateMod #Obligation
Apr 17, 20250+$780,200
Aug 31, 2026P00001-$384,722
Subcontractors 1$155,571 total

Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete

SubcontractorAmount
UEI MEUKRP9H25X1
Provide post-award construction management/inspection support services for overseeing pulverizing, road reconstruction, asphalt surfacing, regrading parking area, drainage replacement, roadway obliteration, revegetation and restoration for duck creek road construction.
$155,571