Awarding Agency
Sub-Agency
Department of the Navy
Start Date
September 8, 2025
End Date
November 4, 2026
NAICS
PSC
Z2ED
Description
THIS DESIGN-BUILD CONTRACT ENCOMPASSES THE COMPLETE REPLACEMENT OF THREE (3) CROWDED STEEL BULLNOSES AT THE DEWATERING DISCHARGE SYSTEM FOR DRY DOCK 6, BUILDING 706, PSNS BREMERTON.
Transactions (1)
| Date | Mod # | Obligation |
|---|---|---|
| Sep 8, 2025 | 0 | +$721,961 |
Subcontractors 1$411,975 total
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
| Subcontractor | Amount |
|---|---|
UEI CCCHALNKQKV9 Provide work plans, lift plans, and ahas (activity hazard analysis). provide lifting services for materials and equipment (less than 2000 pounds). establish and maintain bmps (best management practices) for discharge tunnel work. provide single marine chemist clearance for culvert prior to demo; conduct daily gas free clearance and confined space monitoring.
install 36" cofferdam, demo, remove, and dispose of 3 existing steel bullnose sections. provide up to 10
cubic feet of concrete repair within 5' radius of each of the 3 existing bullnose sections. provide and install new
frp (fiber reinforced polymer) bullnose; anchor with 3/8" countersink ss concrete screws. place new, pre-bagged, high performance concrete repair material behind new bullnose and at concrete repair areas. provide testing
and disposal of existing concrete for rcra (resource conservation and recovery act) metals. | $411,975 |