Back to contract actions
Awarding Agency
Sub-Agency
Department of the Army
Start Date
August 15, 2025
End Date
August 10, 2029
NAICS
PSC
M1EA
Description
DESIGN, BUILD, AND COMMISSION A MODERN 155MM LOAD, ASSEMBLE, AND PACK (LAP) FACILITY AT THE IOWA ARMY AMMUNITION PLANT (IAAAP)
Transactions (4)
| Date | Mod # | Obligation |
|---|---|---|
| Aug 15, 2025 | 0 | +$635,200,000 |
| Mar 3, 2026 | P00001 | +$0 |
| Apr 24, 2026 | P00002 | +$0 |
| Jul 29, 2026 | P00003 | +$0 |
Subcontractors 8$449,517,847 total
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
| Subcontractor | Amount |
|---|---|
UEI CGT9HLNKLT98 Design, manufacturing, and installation support for thermal cycling chambers | $11,664,538 |
UEI QHL5DNL1NUK3 X-ray systems, facility commissioning and prove-out services, and permitting consulting services | $20,000,000 |
UEI JQNYSHBF5477 Engineering and design services for the future artillery complex (fac 2.0) contaminated water treatment (cwt) facility at the iowa army ammunition plant (iaaap). | $704,500 |
UEI CGT9HLNKLT98 Engineering services to design modular ovens for a new 155mm load, assemble, and pack (lap) facility at the iowa army ammunition plant (iaaap). | $557,840 |
UEI NSR1ULBVG4S7 Design and construction of the facilities that will house systems to successfully process and produce 155mm artillery at a new load assemble, and pack (lap) facility at the iowa army ammunition plant (iaaap). | $222,675,000 |
UEI LS7QFSL3G4Q5 Consulting support including preparation of project documentation, subject matter expertise, and integrated master scheduling to assist in planning, coordination, and execution of program objectives. | $307,044 |
UEI EW44ECLPXYK1 Design, procurement, manufacture, integration, and installation of multiple systems to successfully process and produce 155mm artillery at a new load assemble, and pack (lap) facility at the iowa army ammunition plant (iaaap). | $181,000,000 |
UEI K6T4THQ5XZ56 Engineering design, process development, and site safety planning to support the design, construction, and commissioning of a new 155mm artillery load assemble, and pack (lap) facility at the iowa army ammunition plant (iaaap). | $12,608,925 |