PIIDW58RGZ26F0135DELIVERY ORDER
$44,784,262.00
Awarding Agency
Sub-Agency
Department of the Army
Start Date
January 14, 2026
End Date
August 31, 2031
NAICS
PSC
1520
Transactions (3)
DateMod #Obligation
Jan 14, 20260+$16,245,740
Jun 30, 2026P00001+$28,538,522
Jul 7, 2026P00002+$0
Subcontractors 16$9,710,059 total

Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete

SubcontractorAmount
UEI U1NDNFGSBWD8
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$1,272,960
UEI CHKUMRQFRMT8
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$38,824
UEI JKZ9KRNBUGT8
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$80,982
UEI C6XNMCVKJSH9
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$1,961,871
UEI X3HAC55NLM68
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$36,369
UEI DJMXCNAWRJU7
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$72,914
UEI G4M3KUF95AL3
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$964,983
UEI C3H5CW3YHJK6
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama
$1,216,500
UEI K4UPNWD7YEB1
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.
$1,418,103
UEI G4M3KUF95AL3
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$627,936
UEI LNHMPKHDLAQ3
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$447,154
UEI LEKLKCFKZ2Q5
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.
$992,852
UEI V1LMQHUZF831
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.
$175,392
UEI HSSTMBL1PFN6
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.
$56,372
UEI EWR1ZRQ2Q6E9
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$66,676
UEI NAJKL26ADJL4
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama
$280,172