FedOps logoFedOps
Back to contract actions
PIIDW58RGZ26F0157DELIVERY ORDER
$11,506,751.00
Awarding Agency
Sub-Agency
Department of the Army
Start Date
May 14, 2026
End Date
May 21, 2028
NAICS
PSC
1520
Transactions (4)
DateMod #Obligation
May 14, 20260+$11,506,751
Jun 1, 2026P00001+$0
Jun 18, 2026P00002+$0
Jun 24, 2026P00003+$0
Subcontractors 10$1,795,547 total

Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete

SubcontractorAmount
UEI D8LDZVAZU3H9
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$79,620
UEI DLKDT5GBNFL1
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$33,067
UEI HQMJUQW8CQF8
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$143,723
UEI EBHFYF38BJ91
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$61,700
UEI FMMAEB6M4C29
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$133,973
UEI KQJTYTVTATY8
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$229,464
UEI GWNNCMEMFCJ5
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$100,632
UEI CASZKA1CMGH3
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$41,949
UEI C2CQHT3K1HE9
Materials in support of prime contract w58rgz-18-d-0001 for the prototype integration facility (pif) at redstone arsenal, alabama.​
$183,751
UEI JR41MJBX4TG5
C-130 improved modular airborne fire fighting system (imaffs) unit #4
$787,668