Awarding Agency
Sub-Agency
Department of the Army
Start Date
December 7, 2018
End Date
March 7, 2023
NAICS
PSC
Y1GA
Description
WEAPONS STORAGE AND MAINTENANCE FACILITY, F.E. WARREN AFB, WY
Transactions (87)
| Date | Mod # | Obligation |
|---|---|---|
| Dec 7, 2018 | 0 | +$145,720,840 |
| Feb 8, 2019 | P00001 | +$109,561 |
| Apr 2, 2019 | A00001 | +$0 |
| Jun 13, 2019 | P00002 | +$150,000 |
| Sep 13, 2019 | A00002 | +$418,809 |
| Dec 2, 2019 | P00003 | +$35,349 |
| Feb 25, 2020 | A00003 | +$67,035 |
| Apr 27, 2020 | P00004 | -$227,293 |
| May 28, 2020 | A00004 | +$59,438 |
| May 28, 2020 | A00005 | +$86,362 |
| May 29, 2020 | P00005 | +$768,520 |
| Jun 25, 2020 | P00006 | +$1,210,196 |
| Jul 13, 2020 | P00007 | +$0 |
| Aug 19, 2020 | P00008 | -$8,380,238 |
| Aug 31, 2020 | A00006 | +$50,731 |
| Sep 4, 2020 | P00009 | +$5,584,859 |
| Nov 3, 2020 | A00007 | +$52,644 |
| Nov 18, 2020 | A00008 | +$31,801 |
| Dec 17, 2020 | A00009 | +$172,057 |
| Jan 5, 2021 | A00011 | +$0 |
| Jan 5, 2021 | A00010 | +$54,398 |
| Feb 5, 2021 | P00010 | +$0 |
| Feb 8, 2021 | A00012 | +$127,594 |
| Feb 22, 2021 | A00013 | +$385,718 |
| Mar 1, 2021 | A00014 | +$171,373 |
| Mar 5, 2021 | P00011 | +$0 |
| Mar 23, 2021 | A00015 | +$123,814 |
| May 3, 2021 | A00017 | +$193,648 |
| May 3, 2021 | A00016 | +$100,000 |
| May 27, 2021 | A00018 | +$0 |
| Jun 9, 2021 | A00019 | +$157,282 |
| Jun 10, 2021 | A00020 | +$0 |
| Jul 6, 2021 | A00021 | +$0 |
| Jul 22, 2021 | A00022 | +$169,582 |
| Aug 5, 2021 | P00012 | +$0 |
| Aug 23, 2021 | P00013 | +$8,924,440 |
| Sep 12, 2021 | P00014 | +$0 |
| Sep 15, 2021 | A00025 | +$59,889 |
| Sep 15, 2021 | A00024 | +$284,134 |
| Sep 15, 2021 | A00023 | +$273,048 |
| Sep 16, 2021 | A00026 | +$125,000 |
| Nov 15, 2021 | P00015 | -$1,034,459 |
| Nov 22, 2021 | P00016 | +$0 |
| Dec 9, 2021 | A00027 | +$164,965 |
| Dec 21, 2021 | A00028 | -$15,545 |
| Feb 18, 2022 | A00030 | +$163,321 |
| Feb 18, 2022 | A00029 | +$213,298 |
| Apr 15, 2022 | A00031 | +$0 |
| Apr 26, 2022 | P00017 | +$300,000 |
| May 18, 2022 | P00018 | +$983,075 |
| May 18, 2022 | A00032 | +$295,768 |
| May 31, 2022 | P00019 | +$0 |
| Jun 23, 2022 | P00020 | -$78,345 |
| Jun 27, 2022 | P00021 | +$0 |
| Jun 28, 2022 | A00033 | +$233,596 |
| Jul 12, 2022 | A00034 | +$304,901 |
| Jul 20, 2022 | A00035 | +$0 |
| Jul 26, 2022 | P00022 | +$160,000 |
| Sep 19, 2022 | A00036 | +$235,549 |
| Sep 22, 2022 | A00037 | +$342,167 |
| Jan 12, 2023 | P00023 | +$0 |
| Jan 13, 2023 | P00024 | +$500,000 |
| Jan 13, 2023 | P00025 | +$179,544 |
| Feb 10, 2023 | A00038 | +$0 |
| Mar 28, 2023 | P00026 | +$1,408,467 |
| Mar 31, 2023 | A00039 | +$406,078 |
| Apr 3, 2023 | A00040 | +$20,044 |
| Apr 17, 2023 | A00041 | +$78,053 |
| Apr 19, 2023 | A00042 | -$62,552 |
| Apr 21, 2023 | A00043 | +$10,711 |
| Apr 21, 2023 | A00044 | +$118,455 |
| May 5, 2023 | P00027 | +$44,215 |
| May 8, 2023 | A00045 | -$26,484 |
| May 12, 2023 | P00028 | -$504,612 |
| Feb 8, 2024 | A00046 | +$7,705 |
| Feb 16, 2024 | A00047 | +$37,139 |
| Apr 2, 2024 | A00048 | +$50,000 |
| Jun 26, 2024 | A00049 | +$44,971 |
| Jun 28, 2024 | A00050 | +$30,000 |
| Aug 2, 2024 | A00051 | -$33,727 |
| Aug 20, 2024 | A00052 | +$16,879 |
| Sep 9, 2024 | A00053 | +$5,000 |
| Sep 13, 2024 | A00054 | +$200,000 |
| Oct 29, 2024 | A00055 | +$17,252 |
| Dec 11, 2024 | A00056 | +$4,223 |
| Dec 19, 2024 | A00057 | +$197,730 |
| Oct 27, 2025 | A00058 | +$202,336 |
Subcontractors 18$119,575,640 total
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
| Subcontractor | Amount |
|---|---|
UEI HB25U4CYQRC4 Change order 1 - 11 not entered in costpoint | $12,375,886 |
UEI X5E3CJ78VKV9 Supply & install all louvers | $2,684,624 |
UEI PU3CVDMZ66H5 Paint & coatings for wsmf project | $821,916 |
UEI F7CKXA2KLWJ9 James drake films - requirements, fixed /hour labor rate contract type - initial contract amount | $162,752 |
UEI TWCYQ9BXGBQ9 Hvac testing and balancing services | $81,825 |
UEI JY25TFKUJ5S8 Furnish doors and provide site supervision at critical phases of the install of the doors and embed steel. | $8,348,890 |
UEI X2TDGLRMNK86 Mod 007 - concrete grinding and concrete driveway repair. | $665,295 |
UEI ZPPTPL6BCUJ3 Initial award - few.s045 - rapid fire protection, inc. (rapid fire has two contracts) | $2,464,225 |
UEI JR32LD45MXF3 Final contract amount is $ 1,662,809.86. | $1,662,810 |
UEI J8C2VP8PW463 Final invoice-payment $433,654.16 / the cents difference is due to the deductions made per line and cp not allowing to zero balance the line, a 0.01 was added instead to be able to make the changes. | $433,655 |
UEI RMCUNHYL7P34 Construction zone and temporary area fencing installation services | $158,902 |
UEI FG2XN77LJ1A8 De-obligate funding for final settlement of all financial issues and obligations with the contract. | $665,517 |
UEI M459W4SCYM19 Po line 353 (mod 33) was missing the 53 cents which was not reflecting the correct balance on the contract mod 037. | $58,939,080 |
UEI DHFASRLMC9T3 Rfp 077 - add vfd to efsmk 101.
note mods 32, 33, 34 & 35 awarded same month and included in new total value. | $22,591,447 |
UEI JTJPYVP7R3T7 Misc. electrical work as directed by fluor
berg electric corp
few.s047
(sub currently not setup as a vender in cp)
1 cent difference in order to close po in the system. | $1,470,219 |
UEI L2ZXJXM2EHR8 Amt reflecting what has been paid on account to even out other mod lines. retainage amt not shown.
mod 20 to descope all remaining balance in contract. -$53,790.56 for a new contract value of $3,861,399.99 | $3,861,400 |
UEI VMZYW5LFFWC9 Cost is for additional ct mobilizations to the site because of changes in the construction sequence of work - fluor decided to take delivery of thew cranes one at a time instead of all three at once. | $2,100,264 |
UEI LXUMZZ3LETN5 Final reconciliation change order to adjust contract to final value. | $86,934 |