Back to contract actions
PIIDW912PM25C0043DEFINITIVE CONTRACT
BERING STRAITS CONSTRUCTION SOLUTIONS, LLC
UEI: XBWADAMX5G14
$3,312,019.00
Awarding Agency
Sub-Agency
Department of the Army
Start Date
October 24, 2025
End Date
October 21, 2026
NAICS
PSC
Y1LB
Transactions (2)
| Date | Mod # | Obligation |
|---|---|---|
| Sep 28, 2025 | 0 | +$3,312,019 |
| Oct 20, 2025 | P00001 | +$0 |
Subcontractors 2$2,342,243 total
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
| Subcontractor | Amount |
|---|---|
UEI YEJ4V2AZ4BH8 Base culvert:
• new culvert installation
o install (2) concrete box culverts at the motsu class yard
• site grading and reconstruction of the trapezoidal channel.
• re-grade (3) storage areas approx. 2 feet deeper and provide positive drainage.
• grade/restore existing drainage ditches
option 1: brunswick road culvert
• installing culvert to include:
o excavation
o culvert installation
o backfill to existing conditions
option 2: trapezoidal channel culvert
• installing culvert at trapezoidal channel
o all earthwork associated including but not limited to excavation and clearing & grubbing.
o culvert installation
o backfill to existing conditions
option 3: track 46 triangle culvert
• installing culvert at track 46.
o all earthwork associated including but not limited to excavation and clearing & grubbing.
o culvert installation
o backfill to existing conditions | $2,173,743 |
UEI CPYNJVPM6NE1 Design of new box culvert.
4.5.2 design of new re-grading layout for storage areas.
4.5.3 design to restore existing trapezoidal channel.
4.5.4 general ditch grading design.
4.5.5 design brunswick road culvert - 3x3 box culvert to replace 24-inch culvert.
4.5.6 design trapezoidal channel culvert – new driveway 36ft 24-inch culvert.
4.5.7 design track 46 triangle culvert – new 2x3, 40ft long culvert at the southern end of region 1 ditch. | $168,500 |