Awarding Agency
Sub-Agency
Department of the Air Force
Start Date
September 25, 2025
End Date
November 22, 2027
NAICS
PSC
Z2JZ
Transactions (2)
| Date | Mod # | Obligation |
|---|---|---|
| Sep 19, 2025 | 0 | +$2,622,198 |
| Dec 18, 2025 | P00001 | +$0 |
Subcontractors 3$1,352,366 total
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
| Subcontractor | Amount |
|---|---|
UEI DQH5LN9QJEC7 1. produce an fpe stamped, fire alarm only engineering package for review by vsfb fd.
2. provide and install an nfpa 72, 2022, and ufc3-600-01 compliant fire alarm only system, per
the approved plans.
a. inclusive of classroom renovation area.
b. removal of existing fire alarm system after cross over.
3. provide final inspection coordination with local ahj. | $133,050 |
UEI KKETR86APJD4 perform as the designer of record (dor) and design quality control manager (dcqm)
for multidiscipline design support services including pm, structural, architectural, and
mechanical.
cad files of the 35% concept design, in compliance with vsfb cad standards, shall
be provided and used as a starting point for this project.
clear redlined record drawings shall be provided by the contractor for incorporation into
as-built drawing updates for the as-built submittal. | $270,010 |
UEI MKRBFSUZKW63 Design phase (electrical power, lighting, and telecom systems):
attend design charrette following kickoff meeting
conduct thorough field investigation including utilities, existing conditions, and electrical power systems
attend two design review conferences
provide load study analysis and calculations for new electrical equipment
provide 35%, 65%, 95%, and 100% electrical design and drawings to be incorporated into design analysis
and project deliverables by others
prepare specifications based on the ufgs and tailored to this project. vsfb standard specifications will be
incorporated as required by others
all drawings will be created in accordance with vsfb cad standards. all gis layers and site plan/floor plan
xrefs to be provided by others
final drawing package will be stamped and signed by an electrical engineer licensed in the state of california
provide record drawings as required
construction phase
demo and rework electrical, lighting, and communications as necessary
cut back and safe off current access control readers and power to door strikes. system to remain operational
outside of scif area.
existing scif vindicator acs and ids systems will be relocated and expanded to support secure area
modification as shown on prelim drawings (devices, wiring, programming, etc).
modify electrical system utilizing existing panels in area to support new electrical configuration.
replace all light switches, outlets, and covers with new.
install new wire basket tray matching existing above t-bar ceiling as well as below raised floor for installation
of new nipr, sipr, jwics cabling.
install new nipr, sipr, jwics communications systems per ufc and classroom requirements, 1 pair per
station.
install floor boxes in classrooms to support power and communications requirements.
install hdmi cabling between instructor station and each wall monitor location in same room. monitors nic.
provide terminations and testing of all new communications cabling, as necessary.
remove and replace lighting with new led lighting throughout area of work only, provide emergency
fixtures as required.
install new led exit signs matching existing style throughout area of work only, as necessary.
install (3) additional uncleared warning lights in corridor only in additional area of work, expanding lights
from previous secure area. relocate light switch as necessary.
install relocation of existing sound masking system to new scif perimeter wall at duct penetrations
provide & rough-in new conduit & boxes only for new fire alarm system in all areas required. | $949,306 |