FedOps logoFedOps
Back to contract actions
PIIDW519TC23F0171DELIVERY ORDER
$345,817,840.11
Awarding Agency
Sub-Agency
Department of the Army
Start Date
March 24, 2023
End Date
February 28, 2029
NAICS
PSC
M1EA

Description

155MM CAPACITY EXPANSION PROJECT FOR M795 AND M1128 TO 65K/MONTH

Transactions (14)
DateMod #Obligation
Mar 24, 20230+$217,676,592
May 31, 2023P00001-$43,187,148
Sep 18, 2023P00002+$0
Dec 22, 2023P00003+$30,078,148
Mar 20, 2024P00004+$28,085,000
Jun 28, 2024P00005+$66,800,731
Sep 26, 2024P00006+$13,301,908
Feb 21, 2025P00007+$4,004,259
Jul 24, 2025P00008+$16,258,268
Sep 26, 2025P00009+$4,887,949
Dec 19, 2025P00010+$18,492,331
Apr 9, 2026P00011-$21,000,000
May 27, 2026P00013+$5,209,901
Jul 2, 2026PZ0012+$5,209,901
Subcontractors 69$41,384,928 total

Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete

SubcontractorAmount
UEI GJD6STHJM3R3
Press rebuild electrical discoveries & np2 bliss press clutch repair
$462,570
UEI ENLWH8J14KF5
Conveyor swing gate to pre-nosing area
$67,492
UEI ENLWH8J14KF5
Concrete measuring pre-nosing
$41,900
UEI LGAMQZZ3MEZ7
Op 320 vlm/ut quarantine programming
$83,381
UEI YEHDSYEAM7F4
New shotblast system + new dust collector and ductwork installation
$829,700
UEI MJRDC3ZCV2X9
Complete chuck package
$138,304
UEI JV3XU5EMBSB1
Conveyor control panel box electric feeds
$41,280
UEI XFQFMTK2MT55
Relocation/rework items for 35k conveyor systems
$67,230
UEI R4C3MNW4FGR6
24-1019 conveyor modification for erie 2 ih
$176,700
UEI RBCFQEG6NTH6
Nosing press 1 se1-800 electrical addendum
$198,200
UEI JV3XU5EMBSB1
Op 30 wall opening and utility relocation & phosphate conveyor install
$231,046
UEI GLVMVBRRGQ13
Op 200, 320, 335 concrete reinforcement
$288,670
UEI ED8BKRCQBFJ7
Change order 1 for nosing press 1 removal/nosing press 2 swap
$369,000
UEI JV3XU5EMBSB1
Np1 conveyor modifications for crown removal
$71,112
UEI RBCFQEG6NTH6
Bliss press loader arm rebuild and reassembly & bliss press transfer exit conveyor rebuild
$235,920
UEI K4ZKQGJW5X88
Loading dock change order 2 - relocation of water lines under loading dock as per usg request/approval.
$140,518
UEI JV3XU5EMBSB1
Concrete replacement for op 200-220 area nte
$234,525
UEI ZJ62QGNT8H55
Engineering services for the additional scope content for the phosphate line.
$354,750
UEI LGAMQZZ3MEZ7
Op 335 final inspect vici vision gage r&r + op 320 ut inspect andec ut machine gage r&r support nte
$157,660
UEI K4ZKQGJW5X88
Loading dock change order 1 - brick infill for windows, change from cmu in original proposal as per shpo
$63,632
UEI GLVMVBRRGQ13
Reinforcement of the existing floor for the removal of nosing press crown 01.
$445,080
UEI JV3XU5EMBSB1
35k pull-ancillary ahead work
$659,544
UEI RCNTW3HMXH34
35k expansion equipment loads
$110,600
UEI EA4AJ7B5KA36
Install of decking between erie ii forge presses.
$77,680
UEI ZJ62QGNT8H55
5019 f conveyors for finish turn north.
$235,000
UEI FP6TVJELTE57
Machine shop bus duct d4 - f4 & bus duct d3 - f3
$135,379
UEI GLVMVBRRGQ13
Machine shop reinforcement engineering and design.
$452,000
UEI JV3XU5EMBSB1
Nosing press 1 utilities relocation and demo
$87,193
UEI C5H6VLXTTL87
Erie press 2 tooling
$170,480
UEI K4ZKQGJW5X88
Construct new loading dock facility in accordance with plans provided by ballina group
$2,668,344
UEI MJRDC3ZCV2X9
Perishable cutting tools for gosiger sat
$113,400
UEI MJRDC3ZCV2X9
35k gosiger open eco list
$1,359,082
UEI RCNTW3HMXH34
35k visitor control center turn-key construction project
$1,347,453
UEI HYNQLKMNHKM6
Program management and engineering services in support of the 35k program.
$432,000
UEI ZJ62QGNT8H55
Elevated guarding for the 35k expansion aei conveyors (additional safety measure)
$101,850
UEI ZJ62QGNT8H55
5005 rough turn (pivot conversion) & 5007 op160 infeed (pivot conversion)
$292,250
UEI J5LVUS5BR133
Labor and equipment for removal of the forge shop rto unit.
$137,500
UEI RYF6GH258MT3
Grieve model hd-484848-ht gas fired box furnaces
$569,518
UEI K9VMHL2MG5X7
155mm m795 ut inspection standard circumferential and longitudinal.
$57,794
UEI VY8MJZGNFXK6
Erie 1 induction heater 5000kva transformer installation.
$325,577
UEI EWBUTL3N8BN5
35k machine shop crysta-apex v9208 measuring machine (cmm machine).
$306,488
UEI EWBUTL3N8BN5
Gaging for 35k machine shop.
$62,873
UEI MJRDC3ZCV2X9
35k machine shop manual lathes.
$561,960
UEI ZDVHY48UFHP5
Increased timeline for installation of press.
$500,000
UEI J5LVUS5BR133
35k machine shop rigging and machine installation.
$597,500
UEI N2B7Y53WSQ13
Electrical disconnect and removal of legacy saw/gantry system.
$47,378
UEI JV3XU5EMBSB1
Gd-ots technical, engineering, design, and turn-key machine installation support for 35k expansion program at scaap.
$6,671,534
UEI K4HHMQSKE814
Taylor winfield spare parts for site acceptance testing (sat).
$43,471
UEI GLVMVBRRGQ13
Steel & concrete work for coolant tank floor reinforcement.
$91,000
UEI RCNTW3HMXH34
Receiving and shipping remaining 35k material in and out of duryea warehouse.
$140,000
UEI RBCFQEG6NTH6
Additional labor to remove crown and slide from np1; relocate crown from np2 (35k np1 crown swap).
$45,000
UEI JV3XU5EMBSB1
Gd-ots technical, engineering, design, and turn-key machine installation support for 35k expansion program at scaap
$4,653,322
UEI MJRDC3ZCV2X9
Gosiger okuma cnc lathes for scaap machine shop
$3,820,801
UEI NN3WKJ4DMEL7
35k expansion erie 2 press tooling
$63,000
UEI XUDFLWN1J667
Erie 2 press tooling - extrude tooling
$53,718
UEI XUDFLWN1J667
Erie 2 press tooling - preform lower tooling
$56,343
UEI WED9AQH81SW3
Erie 2 press tooling - extrude stripper assembly + draw riser assembly
$35,100
UEI RBCFQEG6NTH6
Nosing press #1 -engineering, labor, and materials to rebuild the bed ejector for the se1-800
$88,754
UEI HWKKXCQ45U67
Mettler toledo scale integration with installation, training and runoff of the temporary line
$198,164
UEI NN3WKJ4DMEL7
Erie 2 press tooling - extrude
$43,515
UEI NN3WKJ4DMEL7
Erie 2 press tooling - extrude
$54,430
UEI XFQFMTK2MT55
35k rough turn - mayfran chip conveyor
$319,582
UEI GLVMVBRRGQ13
Loading dock architecture and engineering design
$64,600
UEI GLVMVBRRGQ13
Visitor control center architectural and engineering design
$84,200
UEI MJRDC3ZCV2X9
Eco 06 & 07 rough turn drawer storage for tool trays
$405,521
UEI UNTXVZN8KZZ3
Op.20 saw cell gantry system
$391,500
UEI JV3XU5EMBSB1
Gd-ots technical, engineering, design, and turn-key machine installation support for 35k expansion program at scaap
$7,089,380
UEI MQCQF5MLYWD1
Procurement of shotblast pots
$89,480
UEI ED8BKRCQBFJ7
35k crown removal and reinstall
$775,000