Description
TO PROVIDE ALL LABOR, MATERIAL, PARTS AND EQUIPMENT REQUIRED FOR THE REMOVAL AND REPLACEMENT OF FEED WATER PIPING AT BUILDING 136 PER SOW PROJECT #26PW004 Bldg 136v2. Wage Determination General Decision Number: NY2, latest revision applies and is incorporated. Magnitude of this Project is between $25,000 and $100,000 Period of Performance is 45 Calendar Days from receipt of Notice to Proceed. 100% Payment and Performance Bonds (Performance bonds only if quote is over $150k) are required Technical POC is Michael White. Pricing Arrangement: Firm Fixed Price PLEASE READ THROUGH SOLICITATION AND APPLICABLE DOCUMENTS PRIOR TO REQUEST FOR INFORMATION. ALL REQUESTS FOR INFORMATION MUST BE IN WRITING VIA ELECTRONIC MAIL TO MARIA.D.DECRESCENZO.CIV@ARMY.MIL.
Classification
Place of Performance
Contracting Office
Contacts
Attachments (5)