The purpose of this amendment is to notify interested parties that this solicitation is hereby CANCELLED. The Contracting Officer has determined that the requirement cannot proceed as written after conferring with the technical team and internal subject matter experts. The VA received a large number of Requests for Information (RFI s) associated with this requirement. During the process of researching the responses, the VA determined that the support of a professional architect/engineering (A/E) firm is necessary to address mechanical and HVAC components (among some others) integral to the success of the elevator modernization requirement. A design-build procurement may be more appropriate. However, the VA team will conduct additional research to determine the best path forward, Thank you for your interest in this requirement.