Back to contract actions
Awarding Agency
Sub-Agency
Department of the Army
Start Date
September 8, 2025
End Date
December 24, 2026
NAICS
PSC
Z2DA
Transactions (3)
| Date | Mod # | Obligation |
|---|---|---|
| Sep 5, 2025 | 0 | +$2,931,698 |
| Sep 26, 2025 | P00001 | +$0 |
| Jul 8, 2026 | P00002 | +$315,070 |
Subcontractors 7$2,128,955 total
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
| Subcontractor | Amount |
|---|---|
UEI W82EK3N866D7 Removal and disposal of approximately 15,000 square feet of asbestos and non-asbestos roofing from building 634 down to the concrete decking | $353,979 |
UEI MVCHK5AT5J17 • document review: consultant shall carefully review all provided construction documents in collaboration with the owner to confirm alignment with project requirements and design intent.
• submittal review: the owner and/or contractor shall provide consultant with product submittals for materials proposed for use in exterior enclosure installations. consultant will review and log these submittals to verify that on-site installations conform to the approved design drawings, details, manufacturer installation requirements, and contract.
• mock-up review: consultant shall perform on-site reviews of mock-ups for exterior enclosure elements, as necessary, throughout the course of construction to confirm compliance with design and performance expectations.
• course of construction observations: consultant shall conduct full-time on-site inspections during construction, as needed, to verify the contractor’s compliance with approved project details and manufacturer installation guidelines. these inspections will include review of all roofing operations from tear-off through final installations.
• field observation reports: following each course of construction inspection, consultant shall issue a field observation report including photographic documentation, inspection notes, observed installation methods, and any required corrective actions. | $154,608 |
UEI W3M7Z68F4D32 • relocate (approx. 2’) and replace 12ea. existing roof drains with new.
• add 12 new overflow drains and pipe into primary drain.
• remove and replace (with existing) 3ea. exhaust fans.
• extend 11ea. vents from roof deck to above new roof.
• 12 heat trace connection/tie in points under roof.
• insulation at new piping. | $335,554 |
UEI EZJBXK4JEXH1 Roof demolition: roof related demolition.
• remove and dispose of existing coping and base flashings.
o metal components will be delivered to local recycler in anchorage.
• remove existing roof assembly down to structural decking.
o deposit debris into gc supplied dumpsters.
• provide temporary tie ins and cover during demolition and roof install in order to maintain weather integrity of the roof system.
main building roof areas: fully adhered 3 ply sbs modified built up roof system adhered to structural concrete deck.
• over structural concrete deck install self adhering vapor retarder.
• at structurally sloped roof decks provide r38 polyisocyanurate rigid insulation in 2 layers adhered with manufacturer’s 2 part insulation adhesive.
o install polyisocyanurate insulation crickets with a finished slope of ½” per foot at valleys of structural slope to direct water to roof drains adhered with manufacturer’s 2 part insulation adhesive. cricket valley will be 3/12 slope in plan view.
• install 1/2” densprime cover board adhered with manufacturer’s 2 part insulation adhesive.
• install 3 ply sbs modified built up roof system with white granules meeting or exceeding sri index of 79.
• roof system will be designed to comply with moa and/or ibc wind uplifts which ever is greater and will be ul class a fire rated.
• provide installer’s 5 year standard labor and material warranty.
• provide manufacturer’s standard 20 year ndl labor and material warranty with 120mph wind speed endorsement (note: this is the maximum wind speed provided by the manufacturer).
sheetmetal flashing and trim: install roof related sheet metal flashings as listed below.
• install 24 ga. standard color factory finished coping at roof in compliance with bur manufacturer’s requirements and es-1 compliant for design wind uplift.
parapet framing and raise curbs: provide and install dimensional wood framing to raise parapets and roof curbs to accommodate height of new insulation.
• provide and install a 2x wood framed parapet wall to extend the existing parapet wall approximately 18”-24”.
o insulate wall with batt insulation.
o sheet front and back of parapet wall with ½” cdx sheathing.
o assume standard framing practices for nailing.
o all lumber to pressure treated (ac2) and fasteners will be hdg
o assume ½” wedge style bolt at 24” oc to secure parapet to concrete.
• extend existing roof curbs with 2x dimensional pressure treated lumber approximately 12”.
parapet and wall siding: install standing seam concealed fastener metal panel at existing parapet wall and new extension.
• install self adhering air/moisture barrier at existing parapet wall and the new parapet extension.
• install horizontal hat channel at 2’ oc to accommodate parapet sheathing thickness and a fastening point for metal panel clips.
• install 24 ga. standard color factory finished 1.75”x 16” standing seam snap lock metal panel with concealed clips.
• install 24 ga. standard color factory finished base, corner and penetration flashings associated with metal panel system.
• fill existing scupper holes with insulation.
• provide manufacturer’s 20 year standard material and finish warranty. | $841,000 |
UEI XMGTFN57VQU3 . clean & reseal - aluminum storefront, to include:
1. clean old black silicone from storefront and adjacent surface.
a.dow 795 black
2. exterior storefront to adjacent surface, new sealant.
3. corners of existing storefront window gasket, new sealant.
4. one site visit, local representative for caulking manufacture.
b. clean & reseal – brick to brick at vertical joint, to include:
1. clean vertical joint approximately 4’ apart.
a.dow 795 grey
2. wire brush vertical brick-to-brick, approximate 1/2” joint.
3. one site visit, local representative for caulking manufacture. | $59,200 |
UEI K3T2RC6UN1V6 1. disconnection and reconnection of electrical for rooftop ventilation fans. it is assumed that all existing wiring is code compliant and in good working order, and that extension of existing circuitry to accommodate new curbs may be necessary.
2. demolition of existing rooftop emt conduit and heat trace.
3. provision and installation of new emt conduit in the ceiling space to re-feed new heat trace in six (6) existing roof drains to be relocated. to include splice boxes, end seal kits, conduit, wire, and lighted pilot switches for disconnecting means per nec.
4. provision and installation of up to two (2) new epd breakers and circuits for up to six (6) new overflow drains. to include additional heat trace, splice boxes, end seal kits, conduit, wire, and lighted pilot switches for disconnecting means per nec.
5. remove existing unused electrical rooftop penetrations. | $72,725 |
UEI GAK3VQRQJ8R5 Engineering services:
site report.
design analysis.
65% & 100% design packages. | $311,889 |