Awarding Agency
Sub-Agency
Department of the Air Force
Start Date
May 16, 2025
End Date
September 30, 2026
NAICS
PSC
Z2JZ
Transactions (1)
| Date | Mod # | Obligation |
|---|---|---|
| May 16, 2025 | 0 | +$22,464,081 |
Subcontractors 32$14,844,625 total
Subcontracts reported by primes (FFATA) · first tier only, self-reported, may be incomplete
| Subcontractor | Amount |
|---|---|
UEI YGGFA963MHM8 Division 01 - general requirements (all sections as they relate to your scope of work)
division 03 - concrete (all aspects as it relates to re-shoring requirements for project) | $42,990 |
UEI UJ21LYBGAAB5 Division 01- general requirements (all sections as it relates to your scope of work)
division 08 - openings
08 51 00 - aluminum windows
08 81 00 - glazing | $257,069 |
UEI G4F2ZNEFHE56 General requirments as the apply to their scope
existing conditions - 02 32 00 geotechnical investigations
saw cutting | $109,000 |
UEI Y5KJC4FTCHN6 Division 01- general requirements
division 01 – general requirements (all sections as they relate to your scope of work)
division 09 - finishes
09 22 00 – supports for plaster and gypsum board
09 29 00 – gypsum board | $1,695,232 |
UEI VKH3TRGB9GJ4 Division 01- general requirements
general requirements (all sections as it relates to your scope of work)
division 23 - heating, ventilating & air conditioning (hvac)
23 05 93-testing, adjusting & balancing/or hvac | $66,000 |
UEI MMLAH9MZTGM1 Division 01- general requirements
division 01- general requirements (all sections as it relates to your scope of work)
division 06 - wood, plastics, and composites
06 4116.0 010-plastic, laminate, clad architectural
06 6116-solid surfacing fabrications | $413,000 |
UEI D53AZM9WRSG1 Division 01- general requirements
division 01 - general requirements (all sections as they relate to your scope of work)
division 10 -
10 28 13 - toilet accessories -applicable ufc regulations for corner guards | $47,100 |
UEI C7WHLUL3RN84 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 05 - metals
05 12 00 structural steel | $62,639 |
UEI FC2VKRD7E9D3 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
01 45 35 special inspections | $80,865 |
UEI DDJVAHTNC9C5 Division 01- general requirements (all sections as they relate to your scope of work)
division 07 - thermal and moisture protection
07 24 00 - exterior insulation & finish systems | $604,200 |
UEI RPD2JQ3EB6Z2 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 07 - thermal and moisture protection
07 21 16 - mineral fiber blanket insulation | $67,000 |
UEI MV38C9AGCMP3 Division 01- general requirements
division 01 -general requirements (all sections as they relate to your scope of work)
division 32 - finishes
32 05 33 -landscape establishment
32 84 24 -irrigations sprinkler system
32 93 00-exterior plants | $255,402 |
UEI E292QJRUGXF7 Division 01- general requirements
division 01 - general requirements (all sections as they relate to your scope of work) division 3 - concrete
03 30 00 - cast-in-place concrete
03 30 53 -miscellaneous cast-in-place concrete (as applicable to this scope of work)
03 3 7 13 - shotcrete - (if applicable to this contractor means and methods)
division 31 - earthwork | $924,000 |
UEI CQRZFK7B5HR7 Division 03 - concrete
03 30 00 ast-in-place concrete (as it pertains to your scope of work)
division 07 - joint sealants
07 92 00-joint sealants (as it pertains to this scope of work)
division 09 - finishes
09 65 00 - resilient flooring [while specification section 09 65 00 (resilient flooring) is not included in the gov 't issued project specifications, resilient flooring (including vct and lvt) is identified on the contract drawings. this scope includes all resilient flooring work as shown on the drawings and shall be performed in accordance with standard industry practices and manufacturer guidelines.
ff a formal specification section 09 65 00 is issued after contract execution and includes requirements that materially differ from standard practices or increase the scope of work as currently understood, subcontractor may submit a written request with supporting documentation for consideration of a change in the contract price and/or time. lead builders inc. cannot guarantee that any such request will result in an adjustment but will review the request in good faith.}
09 68 00 - carpeting | $123,976 |
UEI TZY7VQ4DDCJ5 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 02 - finishes
02 08 00 -asbestos specification
02 09 00 - lead in paint specification
02 84 16 - handling of lighting ballasts and lamps containing pcbs and mercury. | $479,940 |
UEI XJM9LL1SKJZ1 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 10 - specialties
10 51 00.00 40- metal lockers (missing specification from contract documents) | $73,475 |
UEI ETT3RZENFD63 Division 01 -general requirements (all sections as they relate to your scope of work)
division 23 - heating, ventilating, and air conditioning {hvac)
23 09 00 - instrumentation and control for hvac
23 09 13 - instrumentation and control devices for hvac
23 09 13 -instrumentation and control devices for hvac and other building control systems | $598,760 |
UEI JEKVSJJZEEN8 Division 0 1 - general requirements (all sections as it relates to your scope of work)
division 03- concrete
03 30 00- cast-in-place concrete (coordination only-provide encased conduit for power & telecom per detail 1 on e-801 and spec 33 71 02 para 3.15)
division 05 - metals
05 05 20 - post-installed concrete and masonry anchors (this contract will need to install anchor bolts in support of equipment being supplied per mfg 's instruction if anchor post installed anchor bolts are required, contractor must install per 05 05 20. this spec needs to be changed to 05 50 13-misc metal fabrication. this contractor to supply and turnover to installation contractor anchor bolts for light standards which fall under 05 50 13) 05 12 00 - structural steel (coordination and supply of materials)
division 07 - thermal and moisture protection
07 84 00 -firestopping (provide fire protection at all penetrations as specified per detail #3 on pg. e-802)
division 08 - openings
08 71 00-door hardware (per spec 26 12 19 pad mounted transformer para 2. 6- contractor to supply padlock for transformer and to follow door hardware spec 08 71 00)
division 09 - finishes
09 90 00 - paints and coatings (c1ordination with other trades only if, per plans and specs it will be this
ivision 26 - electrical
26 05 19. 00 10 - insulated wire and cable
26 05 48 - seismic protection for electrical equipment
26 05 73 - power system study (for coordination purposes only, scope performed by others)
26 08 00 -apparatus inspection and testing (for coordination purposes only, scope performed by others) 26 12 19 - pad-mounted, liquid filled, medium-voltage transformers
26 20 00-lnterior distribution system
26 24 13 - switchboards
26 27 14.00 20-electricity metering
26 51 00 - interior lighting
26 56 00-exterior lighting
division 27 - communication
27 05 13.43 - television distribution system (only as pertains to pathways)
27 01 00 - - building telecommunication cabling system (only as pertains to pathways) | $2,300,000 |
UEI WT78QG6C9QP9 Division 01- general requirements
division oj - general requirements (all sections as they relate to your scope of work)
division 03 - concrete
03 30 00- cast-in-place concrete (as it pertains anchoring materials specific to this scope of work)
division 08 - openings
08 11 13 - steel doors and frames
08 14 00- wood doors
08 34 01 -forced entry resistant components
08 39 54 -blast resistant doors
08 71 00 - door hardware | $195,000 |
UEI N6JSC6GKKF64 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 03 - concrete
03 30 00 - cast in place concrete
03 oj 00.0j -advances composite materials strengthening system | $79,669 |
UEI NM8HVXPHLEK7 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 21 - fire suppression
21 13 13- wet pipe sprinkler system
division 28 - electronic safety and security
28 31 76- interior fire alarm and mass notification system, addressable | $46,300 |
UEI RDHQH6R1NJA3 Division 01- general requirements
division 01- general requirements (all sections as they relate to your scope of work)
division 03 - concrete
03 30 00 - cast-in-place concrete (for coordination purposes only)
cast-in-place concrete (for coordination purposes only)
division 05 - metals
05 05 20-post installed concrete and masonry anchors (as it pertains to this scope of work)
(while specification section 05 50 20-post installed concrete and masonry anchors is not included in the issued project specifications, concrete and masomy anchors are a normal process within the hvac and hvac piping installations and is shown on the drawings and shall be pe1formed in accordance with standard industry practices and manufacturer guidelines. if a formal specification section 05 05 20 is issued after contract execution and includes requirements that materially differ from standard practices or increase the scope of work as currently understood, subcontractor may submit a written request with supporting documentation for consideration of a change in the contract price and/or time. lead builders inc. cannot guarantee that any such request will result in an aqjustment but will review the request in good faith.)
05 12 00 - structural steel
division 07 - thermal and moisture protection
07 84 00 - firestopping
division 08 - openings
08 31 00-access doors and panels
08 91 00-metal wall and door louvers.
division 09 - finishes
09 90 00-paints and coatings (for coordination purposes only)
division 13 - special construction
13 48 7 3 - seismic control for miscellaneous equipment.
division 22 - plumbing
22 00 00 - plumbing, general purpose. (for coordination purposes only)
division 23 - heating, ventilating, and air conditions (hvac)
23 05 15 - common piping for hvac**
23 05 48.19-seismic bracing for hvac
23 05 93 - testing, adjusting, and balancing for hvac (for coordination purposes only)
23 07 00 thermal insulation for mechanical systems
23 09 00-jnstrumentation and control for hvac (for coordination purposes only)
23 09 13-jnstrumentation and control devices for hvac (for coordination purposes only)
23 11 20-facility gas piping. (for coordination purposes only)
23 30 00-hvac air distribution
23 52 00-heating boilers
23 64 26-chilled, chilled-hot and condenser water piping
division 26 - electrical
26 20 00-jnterior distribution system. (for coordination purposes only) | $2,681,755 |
UEI JNDAWNWKQBF4 Ivision 01- general requirements
division oj -general requirements (all sections as they relate to your scope of work)
division 22 - plumbing
22 00 00 - plumbing, general purpose
division 23 - heating, ventilating, and air conditioning (hvac)
23 11 20-facility gas piping
division 31- earthwork
31 00 00 - earthwork
division 33 - utilities
33 46 16 - subdrainage piping | $1,128,661 |
UEI U4T6EFKQF563 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 08 - openings
08 11 13 steel doors and frames
08 14 00 wood doors
08 39 54 blast resistant doors
08 71 00 door hardware | $227,135 |
UEI DG5QBLL6M5M1 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 07 - thermal and moisture protection
07 84 00- firestopping
division 21 - fire suppression
21 i 3 13 - wet pipe sprinkler systems, fire protection | $149,700 |
UEI PWGMV2K3WD14 Division 01- general requirements
general requirements (all sections as they relate to your scope of work)
division 07 - joint sealants
07 92 00-joint sealants (as it relates to your scope of work)
division 09 - finishes
09 30 10- ceramic tiling | $277,200 |
UEI LSG1NKYVNVE1 Division 01- general requirements
division 01 - general requirements (all sections as they relate to your scope of work)
division 07 - thermal & moisture protection
07 52 00 -modified bitmus membrane roofing [while specification section 07 52 00 (modified bitmus membrane roofing) is not included in the gov 't issued project specifications, there are specific statements made within the drawings spec(fying the pvc roofing is to be installed. note #150 on page a-105 within the same document, identifies the contractor is to install an overlay singly ply (pvc) roof system, to include flute filler polyisocyanurate insulation, ½" dense decking and single ply pvc membrane 80 mil thick (redwood color) with ribbed decor. this scope includes all required work as shown on the drawings and details within drawings and shall be performed in accordance with standard industry practices and manufacturer guidelines. | $283,864 |
UEI N1G9YNJLB9E9 Division 01- general requirements
division 01 -general requirements (all sections as they relate to your scope of work)
division 03 - concrete
03 30 00 - cast in place concrete
division 31- earthwork
31 00 00 - earthwork
31 05 13.13 - geotextiles for earthwork
division 32- exterior improvements
32 01 17.61-sealingcracks in asphalt paving
32 05 33-landscape establishment (as it pertains to this scope of work)
32 11 20 - base course for rigid and subbase for flexible paving
32 12 13 -bituminous tack coats
32 12 16.16 - road-mix asphalt paving
3 2 15 00 -aggregate surfacing
32 16 19-concrete curbs, gutters and sidewalks
32 17 23-pavement markings | $873,027 |
UEI C12KE5EJ5HM8 Division 01- general requirements
division 01 -general requirements (all sections as they relate to your scope of work)
division 07 - thermal and moisture protection
0 7 84 00 - fires topping -as it pertains to this scope of work
division 26 - electrical
26 20 00 - interior distribution system -as it pertains to this scope of work
division 27 - telecommunication
27 04 13.43 - television distribution system
27 jo 00-building telecommunication cabling system
division 33 - utilities
33 82 00 - telecommunications outside plant osp (install of cabling only i underground pathway by others) | $119,323 |
UEI HEDEW4W6DEE5 Division 01- general requirements
division 01 - general requirements (all sections as they relate to your scope of work)
division 09 - finishes
09 90 00 - paints and coatings | $368,815 |
UEI NJYXLLZC4ZT5 Division 01- general requirements
division 01-general requirements (all sections as they relate to your scope of work)
division 23 - hv ac
23 05 93 -testing, adjusting and balancing/or hvac
23 08 00- commissioning of mechanical and plumbing systems
23 09 00 - instrumentation and control for hva c
division 26 - electrical
26 08 00 -apparatus inspection and testing
26 51 00-jnterior lighting
26 56 00-exterior lighting | $31,550 |
UEI ZUVAACY7KBG1 Division 01- general requirements
division 01 - general requirements (all sections as they relate to your scope of work)
division 07 - thermal & moisture protection
section 07 84 00-firestopping (as it applies to your scope)
division 21 - fire suppression
section 22 13 13 -wet pipe sprinkler system, fire protection (as it applies to your scope)
division 25 - integrated automation
section 25 05 11 - cybersecurity for facility-related control systems (as it applies to your scope)
division 28 - electronic safety and security
section 28 31 76-interior fire alarm and mass notification system, addressable | $181,978 |